Laytime, Demurrage & Despatch: Complete Calculation Guide
Laytime, demurrage, and despatch are among the most commercially significant concepts in voyage chartering. Getting these calculations right — or wrong — can mean tens of thousands of dollars difference on a single voyage. This guide explains the key clauses, the NOR process, and how to calculate each with worked examples.
Reference basis: IMO/COLREG/STCW concepts, nautical practice, approved ship documents, and CaptainCalc calculation notes. Always verify operational decisions with official sources.
1. What Is Laytime?
Laytime is the period of time agreed in a voyage charter party during which the shipowner makes the vessel available for loading or discharging cargo, without additional charge. It represents the "free time" the charterer has at the port.
Laytime is normally expressed as:
- A fixed number of days or hours — e.g., "5 weather working days"
- A rate-based quantity — e.g., "at a rate of 2,000 MT per weather working day"
Example: If 50,000 MT of grain is to be loaded at 5,000 MT/WWD, the allowed laytime is 50,000 ÷ 5,000 = 10 WWDs.
Why Laytime Matters
On a typical Panamax bulk carrier carrying 70,000 MT of grain:
- Demurrage rate: $15,000 per day
- 1 day of delay = $15,000 loss for the charterer
- A dispute over 3 days = $45,000 — more than the broker's commission
Accurate records and correct laytime calculation protect both parties.
2. Notice of Readiness (NOR)
The Notice of Readiness (NOR) is a formal declaration by the master that the vessel has arrived at the port/berth and is in all respects ready to load or discharge. Tendering the NOR is the trigger event that starts the laytime clock — but only after certain conditions are met.
NOR Requirements
For NOR to be valid, the vessel must typically be:
- Arrived — at the agreed location (port, berth, or anchorage depending on charter party)
- Ready — holds clean and ready to receive cargo; documentation in order
- At the disposal of the charterer
Arrived Ship Concepts
| Charter Party Type | Vessel Is "Arrived" When… |
|---|---|
| Port Charter Party | Vessel is within the commercial area of the port (even at anchorage) |
| Berth Charter Party | Vessel is secured at the designated loading/discharging berth |
| WIBON (Whether In Berth Or Not) | NOR can be tendered at anchorage; laytime runs even before berthing |
NOR Time — When Laytime Begins
After NOR is tendered, there is often a notice period before laytime commences:
- 6-hour notice: Laytime begins 6 hours after valid NOR is tendered
- 24-hour notice: Laytime begins at 08:00 on the next working day
- WIPON (Whether In Port Or Not): Laytime counts from NOR if already in port
3. Key Laytime Clauses Explained
| Abbreviation | Full Term | Meaning |
|---|---|---|
| WWD | Weather Working Day | Time lost due to bad weather is excluded from laytime |
| SHINC | Sundays & Holidays Included | Laytime counts on Sundays and public holidays |
| SHEX | Sundays & Holidays Excepted | Sundays and holidays do not count as laytime |
| SHEX EIU | SHEX Even If Used | Holiday is excepted even if cargo work was done |
| FHEX | Fridays & Holidays Excepted | Common in Muslim-majority ports (Friday = rest day) |
| WIBON | Whether In Berth Or Not | Laytime starts even if vessel is waiting at anchor |
| WIPON | Whether In Port Or Not | Laytime starts as soon as NOR is tendered, anywhere |
Practical tip: Always read the full charter party carefully — the combination of clauses determines what counts as laytime. "5 WWD SHEX EIU" is very different from "5 days SHINC".
4. How to Calculate Laytime Used
Laytime used is calculated from the Statement of Facts (SOF) — the official port log of all events. Every period is assessed to determine whether it counts as laytime or is interrupted/excepted.
Step-by-Step Method
- Start from the moment laytime commences (after valid NOR + notice period)
- Work through the SOF chronologically, hour by hour
- For each period, decide: Does this count as laytime? (Yes/No/Partial)
- Periods that do NOT count: bad weather (if WWD), SHEX periods, breakdowns of ship's gear
- Periods that DO count: all working periods, breaks due to charterer's fault, time during SHINC days
- Sum all counting periods to get total laytime used
Worked Example — Laytime Calculation
Charter Party Terms: 3 WWD SHEX EIU | Demurrage $8,000/day | Despatch $4,000/day (half demurrage)
| Date / Period | Event | Hours Counted | Reason |
|---|---|---|---|
| Mon 08:00 – Mon 18:00 | Loading in progress | 10.0 | Working time counts |
| Mon 18:00 – Mon 22:00 | Rain — operations stopped | 0.0 | WWD — bad weather excluded |
| Mon 22:00 – Tue 08:00 | Night — no operations | 10.0 | Counts (charterer's responsibility) |
| Tue 08:00 – Tue 17:00 | Loading in progress | 9.0 | Working time counts |
| Tue 17:00 – Wed 08:00 | No operations / night | 15.0 | Counts |
| Wed 08:00 – Wed 14:00 | Loading complete | 6.0 | Counts until last line |
| TOTAL LAYTIME USED | 50.0 hrs = 2.083 days | ||
Laytime Allowed: 3 WWD = 72 hours
Laytime Used: 50 hours = 2.083 days
Result: Time saved = 72 − 50 = 22 hours = 0.917 days → Despatch applies
5. Demurrage Calculation
Demurrage is the penalty payable by the charterer to the shipowner when the vessel is kept at port beyond the agreed laytime. It compensates the owner for the ship's lost earning time.
Demurrage Formula
Demurrage = (Laytime Used − Laytime Allowed) × Daily Demurrage Rate
Worked Demurrage Example
Scenario: Panamax bulk carrier, 70,000 MT iron ore, port of Rotterdam
- Laytime allowed: 4 days (per charter party)
- Laytime used: 5.75 days (from SOF)
- Demurrage rate: $12,000 per day
Calculation:
- Time on demurrage: 5.75 − 4.0 = 1.75 days
- Demurrage owed: 1.75 × $12,000 = $21,000
Important: "Once on Demurrage, Always on Demurrage"
This fundamental principle means that once laytime has expired and demurrage begins, exceptions such as SHEX or WWD clauses no longer apply. Demurrage runs continuously, 24 hours a day, including Sundays and holidays, until loading/discharging is complete.
This is one of the most commercially important rules in chartering — bad weather after laytime expires does NOT stop the demurrage clock.
6. Despatch Calculation
Despatch is the financial reward paid by the shipowner to the charterer for completing cargo operations faster than the agreed laytime. It incentivises efficient port operations.
Despatch Formula
Despatch = (Laytime Allowed − Laytime Used) × Daily Despatch Rate
The despatch rate is typically half the demurrage rate ("despatch money at half demurrage"), though some charters specify a fixed despatch rate.
Worked Despatch Example
Scenario: Handymax bulk carrier, 45,000 MT grain, port of Santos
- Laytime allowed: 5.0 days
- Laytime used: 3.5 days
- Demurrage rate: $10,000/day → Despatch rate: $5,000/day
Calculation:
- Time saved: 5.0 − 3.5 = 1.5 days
- Despatch owed: 1.5 × $5,000 = $7,500 (paid by shipowner to charterer)
Despatch on All Time Saved vs. Working Time Saved
| Term | Meaning |
|---|---|
| All Time Saved (ATS) | Despatch includes all saved time including Sundays, holidays and non-working periods |
| Working Time Saved (WTS) | Only working hours count for despatch — Sundays/holidays excluded even if saved |
All Time Saved is more favourable to the charterer. Most modern charter parties specify which applies — if silent, "all time saved" is generally presumed.
7. Statement of Facts (SOF)
The Statement of Facts is the chronological port log recording every event during the vessel's port stay. It is the primary document used to calculate laytime.
What SOF Must Record
- Date and time of arrival at port / anchorage
- Date and time NOR tendered and accepted/noted
- Date and time of berthing / first line ashore
- Start and end times of every cargo operation
- All stoppages: reason, duration (bad weather, gear breakdown, rain, strikes)
- Shift changes, meal breaks (if excluded by charter party)
- Date and time of last line / departure
Who Signs the SOF?
The SOF must be signed by the master (or Chief Officer) and the charterer's agent. The master should carefully review all entries before signing — a disputed SOF entry can lead to lengthy arbitration. If an entry is incorrect, the master should note objections in writing at signing time.
Time Bar Clauses
Most charter parties contain a time bar clause (e.g., "demurrage claims must be submitted within 90 days of completion of discharge"). Missing the time bar can make a valid claim unenforceable. The master should ensure the shipowner/manager receives all SOF documentation promptly.
Frequently Asked Questions
Sources and verification
Use these references as the starting point for verification; always follow current flag-state, company, port, and approved shipboard documents for operational decisions.